Engineering, Procurement, and Construction (EPC) Agreement

This EPC Contract is made on Agreement date, by and between Employer (Name) (Party A) , and Contractor (Name) at (Party B) Venue.

Whereas,

Party A, as the owner of the project at End customer, has agreed Party B to be the EPC general contractor of the project.

Party B agrees to undertake this project. Pursuant to provisions contained herein, Party B will commit to the civil works, equipment procurement, transportation, installation and commissioning, and test run etc. The project is one turn-key project, and Party B is responsible for the quality, safety, duration and cost of the project.

Pursuant to “PRC Contract Law” and “PRC Construction Law” and applicable laws, regulations, and principles, on the basis of equality, fairness and in good faith, Party A and Party B agreed the following agreement:

Project Overview

Project name: Project name

Project location: Project location

Project content: Party B is contracted with construction of CDQ systems CDQ and waste heat power generation projects at End customer, including First system and Second system. Party B is responsible for civil works, equipment procurement, transportation, installation and commissioning, and test run etc. required for the operation of the CDQ and waste heat power plants.

Scope and Pattern of Project

Scope of work by Party B (contracting scope)

Party B undertakes the project as an EPC contractor and shall be responsible for civil works, equipment supply, equipment installation and commissioning, and final acceptance pursuant to national standards and project design approved by Party A.

The scope of work by Party B is as follows:

All civil works included in the CDQ and waste heat power generation project;

Equipment (including imported equipment), installation material procurement, manufacture supervision, unloading, and storage, ensuring all equipment and products are up to standard;

Project construction and management;

Equipment installation;

Hot test run;

Commissioning;

Delivering the final acceptance report and documents to Party A.

The specific work scope is as follows:

Party B is responsible for the design and related costs;

Party B is responsible for civil works;

Party B is responsible for equipment procurement, installation and commissioning, tests, flaw detection for special facilities, pressure containers and pipes, and bearing the costs;

Party B is responsible for the commissioning, and bearing the costs;

Party B is responsible for application of others other than application of power grid connection (special construction permits, such as pressure containers and pipes);

Specific construction quantities are shown on the civil work and installation drawings (Party B is responsible for the drawing design). Party B is responsible for civil works, installation, and procurement of equipment for power plants, main and auxiliary materials;

Party A is responsible for the government approval of the project, application of access systems, remote control and communication systems, and bearing the costs;

Party B is responsible for the fuel costs during commissioning and test runs.

Contracting pattern: civil works, equipment procurement, installation, project duration, costs, quality, safety, services, and turn-key project.

Contract duration

The commencement date of the project is the Commencement period calendar day(s) after the contract is signed.

Project termination date: the day after Test run hours of test run of the power plants.

Total construction period: Total reconstruction period for single system.

Project delivery day: final acceptance shall be conducted within Final acceptance period after the Test run hour test run. The delivery day is the day all parties complete the acceptance and sign on the acceptance report.

Quality standard

Project quality standard: the project will be accepted in accordance with the Quality standard. Party B shall provide qualification certificates as per relevant department’s requests and cooperate with Party A to provide completion and acceptance documents.

Contract price

Total contract price: Total contract price, RMB First system price for First subsidiary, and RMB Second price price for Second subsidiary;

The total contract price is the lump sum price including civil works, equipment supply, procurement of main and auxiliary materials, transportation, unloading of equipment and materials, second-time transportation, storage, labor, management, installation and commissioning, safety, water and electricity fees during installation, fees for maintenance, insurance, profit, taxes, provisions, risks, and fees for transportation, installation and disassembling of large machineries.

Total contract price also includes extra costs for remote construction, temporary facility fees, antifreeze costs, safety fees (safety, environment protection and special needs), construction costs, night-time construction costs, high-rise construction costs, scaffold assembling and demolition costs, boiler pressure and pipeline checking costs, single test run, hot-test runs and maintenance costs. It also includes second-time transportation costs of equipment and material, increase in engineering costs caused by material price difference, changes and other costs.

Increase and reduction of engineering costs due to change of detail design and markets shall be considered.

Payment

The payment shall be made in tranches for two systems at First subsidiary and Second subsidiary. The payment shall be made as follows:

Party A shall pay Advance payment percentage % of the price for a single system as the advance payment, which is RMB Advance payment, to Party B within Advance payment period after the contract is signed;

Party A shall pay Progress payment percentage % of the price for a single system as the progress payment, which is Progress payment amount, to Party B after the primary design is approved;

Party A shall pay Main equipment percentage % of the price for a single system, which is Main equipment amount, to Party B Main equipment payment period after the main equipment is ordered.

Party A shall pay Civil works percentage % of the price for a single system, which is Civil works amount, to Party B within Civil works payment period after the civil works started and equipment contract is signed.

Party A shall pay Installation payment percentage% of the price for a single system, which is Installation payment amount, to Party B after the installation started and before main equipment is supplied.

Party A shall pay Complete installation percentage % of the price for a single system, which is Complete installation amount, to Party B within Complete installation payment period after the installation is completed and ready for test runs.

Quality guarantee: Quality guarantee percentage % of the price for a single system, Quality guarantee amount of bank guarantee.

Documents that constitute the contract include:

The contract

Terms of the agreement

Appendixes of the contract

Applicable standards, regulations and technical documents

Written documents of negotiation and modification by both parties are part of this contract.

In accordance with the contract, Party B shall perform the contracting service till delivery of the project and be responsible for quality warranty within the warranty period. The warranty period is Warranty period after acceptance after the power plants are accepted or Alternative warranty period after the power plant construction is completed.

Party B promises to monitor and manage the project during its performance period, Party B shall:

Submit project progress report;

Accept the inspection to all parts of the project. For any unqualified parts, Party B shall redo it.

Accept the supervision during the construction period and rectify the issues raised.

Party A commits to Party B to make payment pursuant to the schedule and method stated herein. Representative of Party A will discuss the issues raised about the construction. Party A is responsible for the project management fee.

The contract is executed effective as of the date representatives or agencies of both parties signed and sealed.

Terms of the contract

Documents of the contract

Documents of the contract and sequence interpretation

Documents of the contract shall be interrelated and mutually explanatory of one another. Documents comprising the contract and the priority are as follows:

The contract

Terms of the contract

Appendix of the contract

Applicable standard, specifications and related technical documents

For implementation of the contract, written agreements or documents related to both Party A and Party B’s engineering negotiation, supplement and modification are deemed as part of the contract.

Language and applicable laws, standards and rules

Besides English, the contract also uses the language of Second language .

Applicable laws and rules

Laws and administrative regulations required to be expressed clearly are: Applicable laws and other current applicable national laws and local regulations.

Applicable standards and specifications

Applicable standards and specifications: Applicable standards and specifications and related standards and rules etc.

Date of Party A to provide the standards and regulations: Standard date

General rights and obligations of both parties

Party A will accredit engineers.

Party A’s work

Party A shall complete the following works in accordance with the stipulated time and requirements:

Required conditions of the construction site and time of satisfying the conditions: within Commencement conditions period prior to the commencement of construction.

Arrange the water and electricity line, Party B shall connect the line to the required place for construction requirements.

Roads connection time and requirements between the construction site and public ways: within Commencement roads connection prior to the commencement of construction.

Provide information of engineering geology and underground pipeline: within Commencement geology information prior to the commencement of construction.

Approval for required certificate and documents construction handle by Party A and completion time: within Commencement approvals prior to the commencement of construction

Examination requirements of standard point and coordinate control point: within Commencement examination prior to the commencement of construction.

Design drawing review and design completion time: within Commencement design review prior to the commencement of construction. (Presided over by Party A)

Take coordination works of protecting underground pipelines, adjacent buildings, structures (including listed buildings) as well as old and famous trees surrounding the construction site.

Based on current conditions of the Plant, provide accommodation and office for the construction works, the deficiency part shall be resolved by Party B.

Responsible for the on-site and entrance security work.

Works stipulated by both parties: Other works

All off-site construction works.

Party A is responsible for coordination works between the owner and Party B.

Works entrusted to Party B by Party A: Entrusted works

Party B’s work

Party B shall complete the following works in accordance with stipulated time and Party A’s requirements

Provide the name and completion date of the plan and statement: Plan name and completion date.

Undertake the safety work of construction and non-night construction lighting: Party A shall be responsible for the coordination. Party B provides and maintains the construction night lighting and the rail facilities. Party B is also responsible for the security in construction site.

Related traffic in construction site, sanitation and noise management procedures handle by Party B: comply with the government and related departments’ regulations for the traffic, noise and environmental protection in the construction site, transact related procedures. Party A shall actively assist Party B, and Party B shall bare all costs arising from it.

Special requirements and fees of completed product: Completed products

Protection of underground pipelines, adjacent buildings, structures (including listed buildings) as well as old and famous trees surrounding the construction site.

Sanitation and hygiene requirements of the construction site.

Other works through negotiation.

Construction design and time limit

Schedule

Party B provides construction design (construction plan) and schedule

Schedule requirement related to group engineering: Schedule requirement.

Time limit exceed

The construction period shall be extended if time limit exceed by the following reasons:

(Construction cannot operate normally by virtue of delay of engineering fees paid by Party A;

Major design changes caused by Party A

Cut-off of water, electricity and gas supply for more than Utility threshold hours in one week which is not Party B’s causes;

Force majeure

Party B shall make a written notice for the construction delay within Delay notice since the date the situations of above 2.1 occur. Party A may issue a confirmation after receiving the report within Confirmation duration, no confirmed or amendments shall be deemed an agreement to the delay.

Quality and acceptance

Party B shall notify to do concealment engineering checks and center acceptance Concealment advance notice hours in advance, the construction shall be continued after confirmation.

Safety construction:

Applicable safety standards

Contract price and adjustment

Contract price

Fixed total price shall be adopted in a stipulated scope for the contract price, taking lump sum fee containing tax, profit and management fees, which include:

Engineering design cost;

Equipment and materials fees used for the power plant; materials including main materials and auxiliary materials;

Party B’s management fees in construction site; technical fees for construction, security costs, temporary facility fees; equipment and tool fees for construction;

Material consumption fees, water and electricity fees for construction, construction fees in rainy season and scaffolding fees;

Unloading fees, inspection and management for all equipment and material arriving to the construction site; (including warehouse or stack place of materials, or board on the shipping vehicle are shipped to the installation place);

The quantity and price difference of the substitution material if material substitution is needed;

Difficulties for specialty-intersecting construction;

Direct and indirect costs on repairing, distribution, change and addition paint for equipment deformation and damage (caused by installation unit);

A variety of construction allowances, such as night duty allowance and health subsidies;

Entrance and exit fees of heavy machinery; addition fees for remote construction;

Policy adjustment made by state; temporary costs for temporary shortage;

Reasonable construction speed-up costs required by Party A, idleness costs caused by equipment delivery delay;

Clean-up fees of the installation site; scrap removal within Scrap removal km; pollution discharge fees of engineering;

Fees of special tool for installation, production fees of tire tool; flat roof building and teardown fee;

Fees for Sub-system’s non-load joint test, entire start (load linkage test) and debugging test;

Addition labor cost and machinery cost for installation and production caused by low efficiency by virtue of hostile environment;

Cost for road maintenance, road transportation management, insurance, and vehicle usage happen in machine-team of construction;

Costs caused by water and electricity cut-off; addition fees for exceeding rated water;

Contract price and other adjustment factors stipulated by both parties

Either party shall not change the contract price except for the following situations and adjustable items pursuant to provisions contained herein.

Increase or decrease of engineering costs exceeds Price adjustment threshold% of the engineering’s total price and confirmed by Party A (including change of the field construction and illustration);

Increase or decrease in number of equipment with the approved design which is proposed by Party A and confirmed by parties, corresponding increase or decrease could be made;

For any increase or decrease of engineering work on the design change caused by government reason, corresponding adjustment can be made after negotiation through both parties.

Supply of equipment and materials

Party A will not provide any materials and equipment for this project.

Party B shall purchase materials and equipment.

Party B agreed: Party B shall provide all equipment relevant to field construction, CDQ system and power plant, cable, cable tray, insulation materials for insulation works, all valves and accessories, all auxiliary equipment as sheets, tubes, profiles, main materials, secondary steel and so on.

Party B shall provide materials warranty and product certificate for purchased equipment and materials.

Major auxiliary equipment purchased by Party B shall be provided by quality, reputable manufactures and design institute. Otherwise, Party B shall make free replacement for products and equipment approved by Party A without preconditions.

Final acceptance and settlement

Party B agrees to provide built drawings: Party B shall submit Built drawings copy copy of build drawings, full completion data in Completion data copies quadruplicate and all electronic copy (provide by institute) to Party A; Submission time: within Submission period since date of completion and commissioning.

1.2 Completion conditions for the project: pursuant to relevant regulations of completion and acceptance conditions of the nation, Party B shall provide Party A one copy of full build drawings, completion data in quadruplicate and application report of completion and acceptance. Party A will identify and assess with quality supervision departments.

1.3 Project has single-unit operation and no-load test conditions, and Party A shall be informed Test advance notice hours early. The notice includes: test content, time, location, engineering test record by Party B and so on. When the test passed, Party A or its representative shall sign on the test record.

At the backfill of hidden civil engineering, Party B must inform Party A and supervisor Hidden work acceptance notice hours before the acceptance (include the name, time and location of the hidden project), the hidden project shall be deemed qualified if Party A does not appear on the scene. Installation works with subsystem test conditions: Party B arranges the test and informs Party A with a Subsystem test notice hours notice which includes: test content, time, location and preparatory work by outsourcer. Three parties sign the test record when the test passed and final acceptance may be started.

The field construction shall have a pass rate of Field construction rate%, other non-main production shall have a pass rate of Non-main production rate%. The installation works by Party B shall have a pass rate of Installation works rate %, the main production system should have a good rate of acceptance with no less than Main production rate%. If Main production rate % cannot be met, a penalty of Low acceptance penalty % of the total cost will be charged.

After completion and acceptance of the project, Party B shall prepare the completion of the project accounts and submit to Party A for approval.

Organization, coordination and technical guidance when the full system was tested (load linkage test): Party A shall provide operating personnel and Party B shall be responsible for commissioning and specific implementation.

Breach of contract, claim, indemnity and reward

Breach of contract:

Party B shall pay an indemnity of Daily indemnity amount for each day of construction delay.

Party B ensures to complete the construction within the contract settled date and strives to complete in advance, expect for force majeure.

Party B will obtain a reward of Daily reward amount for each day in advance.

Any quality issue of the project caused by Party B, or there are quality problems of the equipment chosen by Party B, any loss shall be undertaken by Party B.

Disputes

Both parties agree when there is a dispute happens during the performance of the contract:

Be conciliate by relevant authorities

If any dispute is not resolved by friendly consultations within Consultation period after the date such consultations were first requested by a Party, then any Party may submit a lawsuit in the people’s court where Party A locates.

Miscellaneous

Subcontract

Party A has the right to adjust the contracting content if the construction period, quality and condition of the work finished or unfinished do not reach Party A’s requirements. The price difference for the adjusted part is borne by Party B.

Force majeure

Both parties agreed on force majeure: objective situation that cannot be foreseen, avoided or overcome.

Insurance

Two parties agreed to insure the content of this project as follows:

Party A’s insurance content: Party A insurance

Insurance matters Party A entrusted to Party B: Entrusted insurance

Party B’s insurance content: Party B insurance

Guarantees

Each party represents and warrants to the other Party:

(1) Party B provide performance guarantees to Party A in the form of: Performance guarantee, guaranty contract is the annex to this contract;

(2) Other matters agreed by both parties: Guarantee matters.

Others

In the event of any breach of contract, both Parties shall attempt in the first instance to resolve such breach through friendly consultations.

This contract is in duplicate, each party holds one. All of the following are enforceable by law: terms of contract, agreement, plan drawings, construction drawings, tender documents, tender, tender meetings, bid notices and so on. This main contract has the highest effect.

This contract has been executed effective as of the date signed and sealed by both parties; This Contract shall terminate upon the project completion and acceptance and the maintenance period expires.

If there are changes and additions after the contract signed, a supplementary contract or agreement shall be made in a written form which with is enforceable by law and equally binding with the contract.


In Witness Whereof, the undersigned have caused this Instrument to be duly executed and delivered.

Employer (Name)

Employer
Signature pending

Part A signatory name

Part A signatory title

Contractor (Name)

Contractor
Signature pending

Party B signatory name

Party B signatory title

Template screenshot 1Template screenshot 2Template screenshot 3Template screenshot 4Template screenshot 5Template screenshot 6Template screenshot 7Template screenshot 8Template screenshot 9Template screenshot 10Template screenshot 11Template screenshot 12Template screenshot 13Template screenshot 14Template screenshot 15Template screenshot 16

Disclaimer: The original creator, the author of this template, and fynk GmbH are not responsible for any damages or liabilities that may result from using this template. This template should not be considered a substitute for legal advice, and consulting with a legal professional is recommended before use. fynk GmbH, the original creator, and the author do not provide legal advice and will not be held accountable for any legal consequences arising from its use.

More than 1.000 teams chose fynk to outgrow legal chaos.

What an EPC agreement covers and how to use this template

Learn what an EPC agreement is, how the lump-sum fixed-price structure allocates risk between owner and contractor, what the FIDIC Silver Book international standard covers, and how to customize this template for your project.